post-production in-situ conversion

Notes

  • MAN-9250 (2395 Audrey Manor Ct, Waldorf MD, Charles County, JES Manassas, MIR-260381), 2026-10-13: first partially-covered pier line billed as an in-situ post-production conversion. 10/09 visit found 14 of 34 push piers done (in-progress flag, return visit booked, flag cleared + ADM-RTN by design); on the 10/12 return the crew had backfilled ~20 piers before the inspector arrived, against instruction, and showed photos. Darius marked the line Inspected, so no flag existed and the invoice would have gone out at 1x (2,000, ADD-BKFL 1,200, ADM-CERT 12,525. Production days were first set to Darius’s 8 via routes.portal_projects.update_project(production_days=8) + confirm_production_days, because the PRD-DAY SOW line (read 7) is what the invoice bills. ADM-RTN $350 stays suppressed by the production-job rule. Cert still waits on the pier log (0 of 34 logged, asked in manassas-production 10/12 10:17 ET).